Parent Letters
- October 29, 2026 - Building C Demolition
- September 30, 2026 – Inclement Weather Plan During Renovation
- August 21, 2026 – New Bell Schedule and Campus Safety Updates
- August 19, 2026 – Transition Plan Update
- August 6, 2026 – Renovation Update
- July 14, 2026 – Renovation Update
- April, 30, 2026 – Renovation Update
- January 12, 2026 – Shuttle Exercise
- November 9, 2025 – Renovation Update
- May 23, 2025 – Multi-Year Renovation Announced
October 29, 2026 - Building C Demolition
October 29, 2026
Dear Wildcats,
An exciting next step in our campus renovation begins tomorrow as crews start structural demolition of Building C, making way for our new library, kitchen and cafeteria. This work marks important progress toward new spaces where Wildcats will learn, and gather for years to come.
As this phase gets underway, we want you to know what to expect and how crews will manage the work:
- Heavy equipment: Two excavators will be on-site to begin structural demolition.
- Dust control: Crews will use water spray throughout the process to help control dust.
- Construction boundaries: A 6-foot chain-link fence with a green privacy screen separates the construction area from students and staff.
- Debris removal: Trips to haul away demolition debris are scheduled to avoid school arrival, lunch periods and dismissal.
Students should continue using designated campus pathways and remain outside all fenced construction areas.
We look forward to sharing more milestones as our renovated campus takes shape. Visit www.pisd.edu/legendary for project updates, previous letters, frequently asked questions and opportunities to submit questions or feedback.
Thank you for your continued flexibility and partnership as we build on Plano Senior High School’s legendary tradition and create new opportunities for future generations of Wildcats.
Sincerely,
Kennitra Robertson
Principal
September 30, 2026 – Inclement Weather Plan During Renovation
September 30, 2026
Dear Plano Senior High School Families,
With rain anticipated this week, we want to share our inclement weather plan and the steps we will take to help keep students safe and minimize their exposure to the weather during arrival, passing periods, lunch and dismissal.
Due to our extended campus layout and the need for students to transition between buildings using shuttle buses, we have developed procedures for both sides of campus to help ensure safe and efficient transitions during inclement weather. As with any rainy day, we encourage students to come prepared with umbrellas, rain-resistant jackets or other rain gear.
In the event of severe weather, including lightning, we may place the campus on a Hold, following our Standard Response Protocol (SRP), until conditions are safe for students to travel outdoors. During a Hold, students and staff will remain inside, and outdoor transitions will be temporarily suspended. This may result in shuttle delays and adjustments to our daily schedule.
Our teachers and staff will be mindful of attendance and tardies, recognizing that weather-related delays and shuttle transitions may be beyond students' control. We encourage students to continue making every effort to arrive at their classes on time.
Please review the inclement weather plan below and discuss it with your student so they are prepared. We appreciate your continued patience, flexibility and partnership as we prioritize student safety while minimizing disruptions to the school day.
Sincerely,
Kennitra Robertson
Principal
Plano Senior High School Inclement Weather Plan
Buildings A/D/E Side (Including Portables)
Arrival
Students riding buses and being dropped off in the west parking lot off of Independence Parkway will be directed to enter through Entrance A2, the northernmost entrance in Building A. This entrance provides the greatest weather protection for students entering the building. Students arriving through the carpool lane in the south parking lot off of Park Boulevard will enter building A through the south double doors.
Passing Periods
Students using shuttle buses will be released in groups from the north exit of Building A (Entrance A2) to maximize weather protection. Staff members supervising the area will release students to load buses in an orderly manner. During heavy rain, Plano Senior administration will coordinate with transportation staff to modify shuttle routes. Shuttle buses at Building A will proceed to Building H as usual. Shuttle buses coming from Building H will make an additional stop in the East Parking Lot near the pond for students traveling to Buildings D, E and the portables. Students needing to go to H, will board the bus at this stop. The buses will then proceed to their normal Building A drop off before continuing their route back to Building H. Use of the Wildcat Walkway should be limited during heavy rain. Students who choose to use the walkway should have umbrellas or rain-resistant jackets. In the event of lightning, the campus may be placed on a Hold until it is safe for students to travel outdoors.
Lunch
Students using shuttle buses will be released in groups from the northernmost exit of Building A to minimize exposure to the weather. Staff members will release students based on available bus capacity. Additionally, the auditorium may be utilized as a temporary holding area for students during severe weather conditions.
Dismissal
Students using shuttle buses will be released in groups based on the buses that have arrived. Students will exit through the northernmost exit of Building A to maximize weather coverage. Staff members will communicate which buses are present and will only release students assigned to those buses to minimize time spent outdoors.
Building H Side
Arrival
Students may exit vehicles near covered areas adjacent to the carpool, allowing them to enter the building while minimizing exposure to inclement weather.
Passing Periods
Students riding shuttle buses will remain under the covered area or inside the building on the east side of Building H (bus lane) near the cafeteria until a shuttle bus is available. Staff members supervising the area will release students to load buses in an orderly manner. During heavy rain, Plano Senior administration will coordinate with transportation staff to modify shuttle routes. Buses coming from Building H will make an additional stop in the East Parking Lot near the pond for students traveling to Buildings D, E and the portables. The buses will then proceed to their normal Building A stop before continuing their route back to Building H.Use of the Wildcat Walkway should be limited during heavy rain. Students who choose to use the walkway should have umbrellas or rain-resistant jackets. In the event of lightning, the campus may be placed on a Hold until it is safe for students to travel outdoors.
Lunch
Students should remain inside Building H during lunch to avoid unnecessary exposure to inclement weather.
Dismissal
Students should remain under the covered areas near the carpool and bus lanes until their bus or ride arrives. Staff will notify students of which buses have arrived. This will help limit exposure to adverse weather conditions and ensure a safe dismissal process.
August 21, 2026 – New Bell Schedule and Campus Safety Updates
Dear Wildcat Students and Families,
As we continue adjusting to our temporary campus setup, we have made observations, collected data and listened to feedback from students, families, staff and members of our surrounding community. While we spent the past year carefully planning for this transition, we also knew that moving more than 2,000 students through new routines, spaces and processes each day would require ongoing adjustments. Based on what we have learned during the first eight days of school, we have added additional shuttles and made other thoughtful changes to better support student safety, transitions and learning. Thank you for your patience, flexibility and understanding as we continue to evaluate our processes, respond to feedback and work together to make this transition as smooth and successful as possible for our students.
One of those adjustments is to our bell schedule. Through our observations of shuttle runs, we found that students need approximately 10 minutes to transition between buildings. To provide students with adequate time to move safely and efficiently between classes, we have adjusted the schedule to include 12-minute passing periods.
This change allows us to balance two important priorities: providing students enough time to transition safely while preserving as much instructional time as possible. Please reference the new bell schedule here and on our website. We will begin following the new daily schedule on Monday, August 24, 2026.
As we have reviewed our campus operations, we have also received feedback regarding parking, traffic, pedestrian safety and our impact on the neighborhoods surrounding Plano Senior High School. We are asking for the partnership of our students and families in helping us maintain a safe and respectful environment for our students, neighbors and nearby Haggard Middle School.
We have received concerns regarding student vehicles parking in nearby neighborhoods and litter being left on neighborhood streets and in other areas near campus. Please help us maintain positive relationships with our neighbors by following these expectations:
- Students who drive to school must obtain and properly display a Plano Senior High School parking permit.
- Students may park only in designated student parking areas.
- Students may not park in nearby neighborhoods or at the Plano ISD Aquatic Center.
- Students may not park in staff or visitor parking areas, including staff and visitor lots at Haggard Middle School.
- Vehicles parked without authorization may receive warning stickers. Continued unauthorized parking may result in towing at the owner’s expense.
- Students are expected to dispose of trash properly and not leave litter in neighborhoods, streets, parking areas, or around campus.
Students who walk to, from or near campus should use designated crossings and follow crossing-guard directions. Students should not cross streets at undesignated locations or between vehicles.
Families who are picking up students are asked to use appropriate pickup areas, avoid stopping or parking in neighborhoods or along Parkhaven, and avoid picking students up on Independence Parkway. Please follow school staff and crossing-guard directions and remain aware of pedestrians and other vehicles during peak arrival and dismissal times.
Plano Senior High School and Plano ISD will continue to evaluate our bell schedule, shuttle operations, traffic patterns, transportation, and campus-access needs. We are also working to finalize additional signage to reinforce parking, pickup, and pedestrian-safety expectations.
Thank you for your patience, flexibility, feedback, and partnership. We know our temporary campus setup requires adjustments, and we will continue to monitor our processes and make thoughtful changes when needed to provide the best possible experience for our students while remaining a safe and respectful neighbor to our surrounding community.
Sincerely,
Kennitra Robertson
Principal
August 19, 2026 – Transition Plan Update
Plano Senior High School Families,
As we continue adjusting to the temporary split-campus configuration, we want to acknowledge the concerns we have heard regarding transportation, travel time, tardies and student transitions between buildings. We recognize that this arrangement requires additional planning, patience and flexibility, and that some transitions have taken longer than anticipated.
Campus and district staff are closely monitoring routes, passing periods and daily operations. In response, we have added additional shuttle buses to improve transportation between the two locations and will continue making adjustments based on what we observe throughout the school day.
Students will not be penalized academically for delays caused by district transportation or the transition between campuses. We are working with staff to ensure expectations are applied consistently and that students have reasonable time to move between classes. We are also reviewing specific concerns brought to our attention.
For 50 years, Wildcats have met challenges with resilience, pride and excellence. This year may look different, but the standard that defines Plano Senior High School has not changed. We are confident that our students, staff and families will continue to rise to the occasion while working together to make this temporary configuration successful.
We appreciate the constructive feedback and partnership of our families. We will continue listening, responding and improving, with the needs of our Wildcats at the center of every decision.
Sincerely,
Kennitra Robertson
Principal
August 6, 2026 – Renovation Update
Summary: This update explains important changes to campus operations due to ongoing construction and outlines transportation and arrival procedures, shuttle and lunch services, parking locations, front office and clinic access, Chromebook distribution, lunch options (including off‑campus), tutorials and clubs, counseling and student center support, attendance expectations and updated expectations and consequences for personal communication devices during the school day.
August 6, 2026
Dear Plano Senior High School Community,
Welcome to the 2026–2027 school year! We are excited to welcome our new and returning students and families to Plano Senior High School and look forward to seeing many of our students tonight at Cat Camp from 5:30-7:00 p.m. Reference the email that was sent yesterday for more information. I hope everyone had a wonderful summer and was able to spend time doing the things you enjoy. It is always exciting to come together and begin a new school year, even though we know this year will look different.
There have been many changes across our campus since the last day of school. Throughout the summer, construction crews have been hard at work demolishing and rebuilding spaces, while our district facilities staff have worked diligently to prepare both new and existing areas for the start of the year.
We understand that our temporary campus setup may bring questions and require some adjustments along the way, so we appreciate your understanding and flexibility. Our administrative team has been working closely with district departments and campus staff to prepare for this transition and ensure students are supported each day. The information below provides important campus logistics to help students and families feel informed, prepared, and confident as we begin the year together.
To reference previous renovation updates, please see the renovation parent letter web page. You can also find ongoing updates, FAQs and a place to ask questions or leave feedback on our renovation update page.
Transportation
For routing information, please visit our district website at www.pisd.edu.
- Go to www.pisd.edu
- Click the red menu prompt in the upper left hand corner
- Click departments
- Scroll down and click Transportation Services
- Select My Ride K-12
- Create an account to receive routing information
Arrival at Plano Senior High School
Plano Senior High School will have two bus drop-off locations: Building A and Building H. All buses will stop at both locations. Students should remain on the bus until it reaches the building closest to their first class.
Students arriving at Building A may get breakfast at the Building D kiosk. Students arriving at Building H may get breakfast in the Building H cafeteria.
Building A/D/E
- Bus drop-off: West parking lot facing Independence Parkway
- Parent drop-off: South side of Building A facing Park Boulevard
- Only buses may use the bus lane.
Building H
- Parent drop-off: West side of the building
- Bus drop-off: East side bus lane
Wildcat Express Shuttle Service
The district is providing school buses for our campus shuttle service. Shuttle service will be available throughout the school day, including during passing periods, for students who need transportation between buildings. The number of students using the shuttle each period is expected to be minimal, as most students are scheduled to attend classes in one building during the morning and the other building during the afternoon.
Lunch Shuttle Service
Lunch will begin at 11:48 and end at 12:50. Bus service from Building A to the cafeteria located in Building H will begin at this time. There will also be shuttle service for students to go to club activities and/or tutorials during the lunch hour. Additional shuttle service will be provided for students returning from lunch to reach their class in either building. This additional service will begin at 12:40 and continue until 12:55.
After School Pick-up
Buses will pick up students on both sides of campus in front of Building A and Building H. Students must locate their bus number then quickly proceed to the bus. Parent pickup for Buildings A/D/E will be located in the south parking lot facing Park Blvd. Parent pick up for Building H will be located on the west side of Building H. Please see the map linked above for reference.
Lunch
Lunch begins at 11:48 a.m. and ends at 12:50 p.m.. Students on the A, D, and E side of campus may ride the lunch shuttle to the cafeteria in Building H or leave campus for lunch with parent permission indicated in their beginning of the year registration form.
There is outdoor seating available on the south side of the pond for students to enjoy during lunch. Students may also use the lunch shuttle to attend tutorials and club meetings.
For students leaving campus during lunch, we recommend returning to campus by 12:45 p.m. to allow sufficient time to transition from the parking lot to ensure you arrive at your 4th period class before the 12:56 p.m. start time.
Food and Nutritional Services (Breakfast and Lunch Process)
The Plano Senior High School kitchen and cafeteria will undergo a major renovation. While our traditional cafeteria space is being upgraded, Plano ISD Food and Nutritional Services (FANS) will continue providing students with access to hot, nutritious meals throughout the renovation.
Breakfast Service
- Building H will feature a fully operational kitchen and will be open daily, offering a full selection of hot breakfast items.
- For added convenience, FANS will operate a breakfast kiosk in Building D, which will provide a full, hot breakfast for students without requiring them to leave the main campus.
- Breakfast service will begin at 8:20 a.m. and continue until 9:30 a.m. to accommodate students, including athletes and those arriving later in the morning.
Lunch Service
- Building H will be open for full lunch service.
- Transportation will be provided between the main campus and Building H during lunch period.
- Students will continue to have access to a variety of menu choices, including both Traditional and Concept menu options. All serving lines will offer hot entrees, vegetables, fruit and milk.
- Lunch service will be available from 11:48 a.m.–12:50 p.m.
Student Meal Accounts
- Students may continue to use their existing meal accounts during the renovation. Beginning July 15, 2026, families may log into SchoolCafé to complete a free and reduced price meal application for the 2026–2027 school year.
View Menus & Apply for Meal Benefits
- Families can access daily menus, nutritional information, student meal accounts and complete a free and reduced price meal application through SchoolCafé.
Parking
To access Buildings A, D and E, visitor parking and staff parking will be located in the south parking lot between Buildings A and D. Student parking will be located in one area for the 2026-27 school year. Parking for students who purchase a parking pass will be in the East parking lot along Wildcat Way. There will not be student parking at Building H or near the baseball fields. Any students parking on school grounds other than the east parking lot, will be stickered and/or towed. Please note that there is no parking available at the Aquatic Center. Parking permits may be purchased through Rycor and picked up from either student center.
Front Offices & Checking Students In/Out
All visitors must check in upon arrival to campus. The main front office will be located in Building H at 2832 Parkhaven Drive and secondary reception will be located in Building D at 2200 Independence Parkway. Parents can check their student(s) in/out at either location depending on your student’s location at the time.
Clinic
There will be two clinic locations. Students may access the nurse in either Building H or Building A. Our staff will support students with daily needs and are prepared to respond to emergencies. Please see the nurse in Building H to drop off medication. Both nurses will work together to coordinate times for dispensing medication.
Counseling Student Access
Counselors will continue to see students throughout the school day as needed. Students can get a pass from their teachers to go to the Counseling Office and counselors will send for students using office aides. Students can also email their counselors to schedule a time to see them. The Counseling Office will also be open during lunch for students access and is centrally located to all buildings on campus in the portables near Building E.
Chromebook Distribution
During the first week of instruction, Plano Senior High School will distribute Chromebooks according to the following schedule:
- August 12: Students in Building H
- August 13: Students in Buildings A, D, and E during their Social Studies classes
- Dual Credit Students: Students who have a Dual Credit class during their scheduled checkout time may report to Building D during their Dual Credit period to receive their Chromebook.
Each student will be issued a Chromebook, protective case, and charger. Students are responsible for the care of all three items throughout the school year. To ensure they are ready for learning each day, Chromebooks should be fully charged each morning and brought to school daily. We appreciate your partnership in helping students come to school prepared with the technology they need for success.
Tutorials
Each teacher will post their tutorial schedule on their Google Classroom and will be offered before school, after school, or during lunch. Teachers will offer two tutorials per week and additional tutorials can be made available by appointment.
Clubs
Club sponsors will host meetings, typically in their classrooms, and will announce meeting dates, times, and locations in the weekly announcement slides. These slides are shown on Mondays following the verbal announcements.
Please note that all non-curricular clubs must receive administrative approval before conducting any meetings or activities. In addition, parent consent forms must be completed and submitted before students may participate.
Hall Passes/Counselor Passes
Teachers will continue to issue passes to students to see their counselor, administration, or the nurse as needed.
Personal Communication Devices
Texas House Bill 1481 requires students to keep all personal communication devices powered off and stored away during the entire school day while on campus.
This includes cell phones, smartwatches, earbuds/headphones, tablets, smart glasses, and any other personal telecommunication devices.
In Plano Senior High School, students are expected to keep devices powered off and stored out of sight in their backpacks from the time they enter the building until they leave campus at the end of the school day. Devices may not be used during class, passing periods, lunch, or in any common areas.
Campus staff will teach and reinforce these expectations during the first week of school. Students who do not follow the policy will receive progressive consequences, beginning with device confiscation and parent notification, with repeated violations resulting in increasing disciplinary action.
Thank you for partnering with us as we create a focused, distraction-free learning environment for all Wildcats.
For more information regarding Texas House Bill 1481, please visit the Plano ISD Personal Communication Device webpage.
Student Centers
Student Centers in Building A (A128A) or Building H (H111). Our Student Centers are here to support our students and families. Our team can assist with attendance, student IDs, parking, student check-in/check-out, and connecting students and families with their assistant principal.
For your convenience, we have two Student Center locations:
- Buildings A/D/E: Building A, Room A128A
- Building H: Room H111
Students are welcome to visit either Student Center for assistance, regardless of their assigned assistant principal.
Student Management Across Alphas and Campuses
To ensure consistent support for students throughout the school year, our administrative team will be divided between both campuses while maintaining responsibility for designated alpha groups. As principal, I will be officing in Building H while supporting both sides of campus through intentional scheduling to ensure visibility and to maintain consistent connections with all students and staff.
Building H will be supported by Associate Principal Dr. Coryn Prince, Assistant Principal Gary Westbrook, who serves students with last names Dr–La (Pride Student Center), and Assistant Principal Susan Moran, who serves students with last names Ro–Z (Tradition Student Center).
Building A will be supported by Associate Principal Derrian McKinney, Assistant Principal Shanique Leonard, who serves students with last names A–Do (Spirit Student Center), and Assistant Principal Tracy Ryerson, who serves students with last names Le–Ri (Honor Student Center).
This structure is designed to ensure that students, families, and staff have consistent administrative support while providing a strong administrative presence in both buildings throughout the school year.
Attendance Expectations
We want every student to feel connected, supported, and successful at school. Attending class each day and arriving on time helps students stay engaged, build strong relationships, and make the most of every learning opportunity.
Teachers will take attendance during the first 10 minutes of class. Students arriving within the first 10 minutes without a pass will be marked tardy. Students arriving after 10 minutes without a pass will be marked absent.
If your student misses class, please submit an absence note within three school days of the absence. Notes may be uploaded through the Skyward Family Access portal or submitted in person to the Student Centers.
Students arriving late, leaving early, or returning during the school day must check in or out at either Student Center. Students may use either location, regardless of their assigned alpha principal. Following this process helps us maintain accurate attendance records and ensure the safety of all students.
Students may visit either Student Center, regardless of their assigned alpha principal. If your student would like to meet specifically with their alpha principal, please have them email their student’s alpha principal to arrange a convenient time to be called to the Student Center. Families may also email their student’s alpha principal to schedule an in person meeting.
Thank you for your patience, support, and understanding throughout our construction and transition. We hope this information provides a better understanding of campus logistics. Find additional information, including FAQs and a place to ask questions or leave feedback at www.pisd.edu/legendary. We are excited to begin the school year and are here to support students and families. Campus and district staff will be available on the first day to welcome students and help them navigate the campus. We look forward to creating great memories together this year.
It’s a Great Day to be a Wildcat!
Sincerely,
Kennitra Robertson
Principal
July 14, 2026 – Renovation Update
Summary: This update shares current progress on the Plano Senior High renovation, explains how Buildings B, C, E, H and D will be used for the 2026–2027 school year, and outlines key logistics for temporary campus operations, including front office locations, meal service in Building H and a breakfast kiosk in Building D, as well as parking for students, staff and visitors; it also reminds families about the July 22 town hall and August 6 Cat Camp.
July 14, 2026
Dear Plano Senior High School Community,
We are excited to update you on the outstanding progress our staff made in preparing and packing for the Buildings B and C renovations, which keeps the project on schedule. This renovation represents a significant investment in our students and campus, and we are grateful for your continued patience and partnership. We will host a community town hall meeting on July 22 from 6:15–7:00 p.m. in the Building D Auditorium to provide another opportunity to ask questions and learn more about our renovation progress.
Please note the correction that Cat Camp is scheduled for Thursday, August 6, from 5:30–7:00 p.m. This event will give students an opportunity to walk their schedules and get familiar with our temporary campus setup, including both Building H and Buildings A/D/E. Please mark your calendar and watch for more information in the upcoming Back-to-School Newsletter.
To reference previous renovation updates, please see the renovation parent letter web page. You can also find ongoing updates, FAQs and a place to ask questions or leave feedback on our renovation update page.
Current Campus Renovation Progress Update
Building B
After months of planning and coordination among multiple Plano ISD departments, Building B was successfully vacated in early June, marking a major milestone for the Plano Senior High School renovation project. With staff, programs and materials relocated, CORE Construction has taken full possession of the building and demolition activities are now underway.
Over the next year, Building B will undergo a comprehensive renovation that will modernize learning spaces, improve building systems, and enhance the overall student and staff experience. Construction is scheduled to continue through summer 2027, with the renovated facility anticipated to reopen for the start of the 2027–2028 school year.
Building C
Building C, which previously housed the Kitchen/Dining and Library spaces, has been turned over to CORE Construction and demolition is now underway. The existing building will be completely removed to make way for a brand-new Building C that will serve as a central connection between Buildings A and B.
The new two-story facility will feature a modern Kitchen and Dining/Commons area on the first floor, creating a vibrant gathering space for students with scenic views out to the pond. The second floor will house the new library, designed to provide students with enhanced learning and collaboration opportunities.
As construction progresses, this new building will become a key focal point of the renovated Plano Senior High School campus, providing updated spaces that support both academic and student life for years to come. Construction is currently underway, with the new facility scheduled to open at the start of the 2028–2029 school year.
Building H
The former Haggard Middle School, now designated as Building H, will serve as an important part of the Plano Senior High School campus during construction and will be utilized by students and staff for the next two school years.
Rather than installing approximately 70 portable classrooms on campus, Plano ISD elected to utilize this existing facility, which already includes the infrastructure necessary to support instruction, including technology, security systems, communications and building support systems. This approach provides a more permanent and functional learning environment while minimizing disruption to campus operations.
For the 2026–2027 school year, Building H will accommodate most of the programs and classrooms displaced from Building B, as well as functions previously housed in Building C, including the library, kitchen and dining services. Building H will be supplemented by three portables, which will be used for Early Preschool, counselors and six classrooms.
Throughout the summer, district Facility Services staff have been preparing the building for occupancy through painting, floor cleaning and other maintenance activities. CORE Construction is also completing a series of minor modifications to better align the facility with Plano Senior High School’s needs, including selective wall reconfigurations and electrical enhancements. These improvements will help ensure students and staff have a safe, functional and comfortable learning environment while construction continues on the main campus.
Building E: Athletic Addition
The new 104,000-square-foot athletic addition is beginning to take shape. This space will include two new gym floors, a new front entrance to the competition gym and a completely rebuilt Student Activity Center (SAC). You will also see updates to the existing gyms, locker rooms and athletic offices. Significant progress continues on Building E, which is now fully enclosed and air conditioning systems are operating, allowing crews to focus on interior finishes. Work is underway on painting, flooring, tile installation and ceiling systems throughout the facility.
Inside the new indoor practice field, the turf has been installed and crews are currently adding wall padding and athletic equipment. In the storm shelter/practice gym spaces, installation of the wood athletic flooring is underway, with bleachers scheduled to be installed in the coming weeks. Construction activity also continues in the existing competition gym area, where demolition is progressing and new mechanical, electrical and plumbing systems are being installed overhead. On the south side of the facility, foundation work is advancing for the future main entrance and connecting corridor, which will improve access and circulation throughout the campus.
With multiple areas under construction simultaneously, Building E is beginning to take shape and represents one of the most anticipated components of this project. In addition to providing expanded and modernized facilities for Plano Senior High School athletes, the new athletic complex will serve as a prominent gateway to the campus and will be among the first features many visitors experience when attending athletic events and other school activities.
Pond Restoration/Maintenance
Dredging of the pond is now complete. Sediment and debris have been removed, restoring the pond to its original depth and water quality. The removed material is currently contained in dewatering bags onsite, where water is filtering out while solids remain contained. These materials will be removed prior to August 1.
Building D
Construction of the exterior chiller yard is currently underway on the south side of the building. While there is no major interior construction at this time, some electrical work will take place inside the building during the summer. The new HVAC chiller system will be complete prior to August 1, with supplementary electrical work ongoing this summer. No other scope is anticipated until summer 2027.
Summer Front Office Operations
During the summer until the first day of school on August 11, our front office will be in Building H located at 2832 Parkhaven Drive. Beginning on the first day of school and until the Building A renovation is completed, we will have two reception areas, one at Building H and one temporarily at the entrance of Building D.
Food and Nutritional Services (Breakfast and Lunch Process)
The Plano Senior High School kitchen and cafeteria will undergo a major renovation. While our traditional cafeteria space is being upgraded, Plano ISD Food and Nutritional Services (FANS) will continue providing students with access to hot, nutritious meals throughout the renovation.
Breakfast Service
- Building H will feature a fully operational kitchen and will be open daily, offering a full selection of hot breakfast items.
- For added convenience, FANS will operate a breakfast kiosk in Building D, which will provide a full, hot breakfast for students without requiring them to leave the main campus.
- Breakfast service will begin at 8:20 a.m. and continue until 9:30 a.m. to accommodate students, including athletes and those arriving later in the morning.
Lunch Service
- Building H will be open for full lunch service.
- Transportation will be provided between the main campus and Building H during lunch period.
- Students will continue to have access to a variety of menu choices, including both Traditional and Concept menu options. All serving lines will offer hot entrees, vegetables, fruit and milk.
- Lunch service will be available from 11:48 a.m.–12:50 p.m.
Student Meal Accounts
- Students may continue to use their existing meal accounts during the renovation. Beginning July 15, 2026, families may log into SchoolCafé to complete a free and reduced price meal application for the 2026–2027 school year.
View Menus & Apply for Meal Benefits
- Families can access daily menus, nutritional information, student meal accounts and complete a free and reduced price meal application through SchoolCafé.
Parking
- To access Buildings A, D and E, visitor parking and staff parking will be located in the south parking lot between Buildings A and D.
- Parking for students who purchase a parking pass will be in the East parking lot along Wildcat Way.
- There will be no student parking permitted at Building H, which will remain staff and visitor only parking.
Thank you to our students, future students and families for your patience, support and understanding during our construction phase. We are finalizing logistics for daily operations and instructions for navigating our campus to share with you before the first day of school. We can't wait to celebrate the start of a new year with everyone at Cat Camp on August 6, from 5:30–7:00 p.m. Enjoy the rest of your summer break!
Sincerely,
Kennitra Robertson
Principal
April, 30, 2026 – Renovation Update
April 30, 2026
Dear Plano Senior High Community,
We are excited to begin our transition to the 2026-2027 school year! You have likely noticed that our campus continues to evolve as renovation work progresses. We know that a new school year, especially one with changes, can bring both excitement and questions. Our goal is to ensure this experience is as smooth, organized and positive as possible for students, staff and families.
This letter is the first in a series of monthly updates, now through the first day of school, to keep you informed and prepared for the months ahead. Each update will provide timely information on important topics like renovation progress, transportation, daily campus logistics, safety and security, parking and academic support. We are committed to keeping you informed so you feel confident and prepared for the year ahead.
We will also host regular community meetings to share updates and answer questions. Our first meeting will be held on May 13, 2026, at 5:30 p.m. in the cafeteria, and we encourage you to attend. Additional details will be shared soon.
We also look forward to welcoming our new and returning Wildcats during Cat Camp on August 8, 2026. This event will give students an opportunity to walk their schedules and get familiar with our temporary campus setup, including both the main campus and Building H. Please mark your calendar and watch for more information in our summer newsletter.
To reference previous renovation updates, please see the renovation parent letter page. You can also find ongoing updates, FAQs and a place to ask questions or leave feedback on our renovation update page.
Campus Renovation Progress Update
Building E: Athletic Addition
- The new 104,000-square-foot athletic addition is beginning to take shape. This space will include two new gym floors, a new front entrance to the competition gym and a completely rebuilt Student Activity Center (SAC). You will also see updates to the existing gyms, locker rooms and athletic offices.
- The building is now “dried in,” which means the roof, walls and windows are in place to protect the interior from the weather. Interior work is progressing steadily in the SAC, storm shelter, weight room and locker rooms. Electrical, plumbing and mechanical systems are being installed, with power expected by the end of April and air conditioning soon after. Installation of indoor turf in the SAC is expected to begin this week.
- The existing competition gym is undergoing interior demolition, with exterior demolition set to begin next week. The girls locker room was completed in December.
Pond Restoration/Maintenance
- Dredging of the pond is now complete. Sediment and debris have been removed, restoring the pond to its original depth and water quality.
- The removed material is currently contained in dewatering bags on-site, where water is filtering out while solids remain contained. These materials will be removed prior to August 1.
Building D
- Construction of the exterior chiller yard is currently underway on the south of the building. While there is no major interior construction at this time, some electrical work will take place inside the building during the summer.
Renovation Timeline Reminder
- 2026–2027: Building B will undergo renovation. Students and staff will temporarily relocate to Building H (the current Haggard Middle School campus).
- 2026–2028: Building C (cafeteria, kitchen and library) will be demolished and rebuilt. These services will temporarily move to Building H.
- 2027–2028: Renovation shifts to Building A. Programs in Building A will temporarily relocate to Building H once Building B is complete.
- 2028–2029: All students and staff return to the fully renovated campus in August 2028. Building H will then be demolished to make room for the construction of a new tennis court complex, with project completion scheduled for February 2029.
Transportation
- Transportation will be available for both areas of campus: Buildings A/D/E and Building H. Midday shuttle service will operate between locations, and dismissal pickup will be available at both sites. Route-specific information will be shared in August.
Daily Schedule
- Students will begin their day either at Building H or Buildings A/D/E where they will remain through third period. During the lunch block, most students will travel to the other side of campus.
- Lunch will be available in Building H, and students may also choose off-campus lunch if eligible.
- At the end of the lunch block, students will either walk or use shuttle transportation to reach their fourth-period classes. walk from the student parking lot to their 4th period class or utilize the shuttles.
- Most students will remain on that same side of campus fourth through seventh period. Some specialized courses may require additional movement, and time will be built into those schedules. Shuttle service will be available throughout the day to support these transitions.
Thank you for your continued partnership, flexibility and support throughout this important phase for Plano Senior High School. We are committed to clear communication throughout the remainder of this school year and into our transition for 2026–2027. We appreciate all you do for our Wildcats and look forward to finishing this year strong while preparing for a great start in August.
Sincerely,
Kennitra Robertson
Principal, Plano Senior High School
January 12, 2026 – Shuttle Exercise
January 12, 2026
Dear Wildcats,
Tomorrow, we will take an exciting step in preparing for our campus renovation. We will be conducting a practice shuttle exercise between the main Plano Senior High campus and Building H (the current Haggard Middle School site) from about 12:15 to 2:15 p.m. This exercise will help us fine-tune transportation logistics for the upcoming year. You may notice buses running and district staff participating as mock students. This will not disrupt regular classes or activities.
We’re thrilled about the future, and every step we take now is building a lasting legacy for generations to come. Thank you for your ongoing support and enthusiasm as we move forward toward this wonderful new chapter for our school.
Sincerely,
Kennitra Robertson
Principal
November 9, 2025 – Renovation Update
November 9, 2025
Dear Wildcats,
As you may be aware, exciting changes are underway at Plano Senior High School. This year marks more milestones in our multi-year campus renovation, building on important safety and security upgrades like the recently installed entry-resistant film. Enhancements will continue throughout the campus, supporting learning and student life for Wildcats today and for generations to come.
Recent highlights include the completion of our upgraded baseball and softball complex. Construction began in September 2024 and brought the demolition of the original softball field, followed by the creation of a new field closer to the baseball diamond. Both fields now feature new turf, home-side locker rooms integrated into the dugouts, a modern concession stand, new restrooms and an updated ticket entry. Our student athletes began practicing on the new turf in February 2025, and the dugouts, concession stand, and ticket booth were finished in October 2025. The band practice field was also relocated and opened in time for the new school year in August.
Renovations and additions will continue taking place in phases through 2029, each carefully planned to prioritize student safety and minimize disruptions. As work continues, I want to outline a few key updates about the next major steps in our renovation. We appreciate your partnership and positivity as we step into the next chapter of our campus renovation.
Timeline
(Construction timelines are approximate and may change due to factors like weather or other circumstances. We will provide updates should changes occur.)
- 2025–2026: Construction crews have begun foundational work for the new Athletics addition. The storm shelter, which will house two new gyms, is quickly taking shape, while renovations to Building E’s girls’ locker room are scheduled for completion by the end of this year. Next, work will begin on the boys' locker room area, with the competition gym set for renovation starting in March. All additions and upgrades to the Athletic Building are expected to be finished by October 2026.
- 2026–2027: Building B will undergo renovation. During this phase, students and staff from Building B will temporarily move to Building H, the current Haggard Middle School building, fully prepared for Wildcat use once the new Haggard opens.
- 2026–2028: Building C, which houses dining and kitchen spaces, as well as the library, will be demolished and rebuilt from the ground up. These spaces will be temporarily moved to Building H.
- 2027–2028: Renovation work shifts to Building A. After Building B returns to its upgraded facility, students, staff and programs served in Building A will temporarily relocate to Building H.
- 2028-2029: All students and staff will be back on the fully renovated campus in August 2028. Once students and staff have successfully moved out of Building H, it will be demolished to make room for the construction of a new tennis court complex. The entire project is scheduled to be completed by February 2029.
Support and Logistics
- Focused on Safety: Secure pathways, access controls, fencing and supervision will ensure safety everywhere, including Building H.
- Continuity of Learning: Classes, specialized programs and student activities will continue even as some spaces shift or move. Building H is being prepared to keep students comfortable and secure during this transition.
- Shuttle Service: Dedicated shuttles will connect the main campus and Building H, with bell and master schedules designed to ensure everyone has a safe and smooth transition between sites.
- Communication: Stay updated through our central hub, pshs.pisd.edu/renovation, where you’ll find news, photos, FAQs, timelines and a place to ask questions or leave feedback. All messages shared with families will be archived here.
We understand that change can bring questions, especially about safety and routines. Please know our students are at the heart of every decision. While your school days may look different at times, our leadership team is hard at work ensuring every Wildcat’s learning, friendships and daily activities continue to thrive throughout this project. Our goal is to help you make meaningful memories in both beloved and new spaces.
As Wildcats navigating this transition, we have the rare privilege of being among the last to experience a campus that has served our community for fifty years, while also helping to create new traditions for those who will follow. Once a Wildcat, always a Wildcat!
Thank you for your flexibility, patience and Wildcat pride as we invest in our school’s next chapter.
With gratitude,
Kennitra Robertson
Principal, Plano Senior High School
May 23, 2025 – Multi-Year Renovation Announced
Dear Plano Senior High Community,
As you are aware, Plano Senior High is preparing for a major, multi-year renovation that will enhance our campus and learning experience for years to come. As we begin this journey, we want to open the door to clear, ongoing communication about the changes ahead and the thoughtful planning already underway.
Starting in the 2025-2026 school year, you will see significant activity on our campus as we launch the first phases of construction. The renovation will occur in carefully planned stages through 2028, with each phase designed to minimize disruption and maintain the high-quality educational experience our students deserve.
Key highlights from the phased plan include:
- Upgrades to athletic facilities, including baseball/softball fields and new band practice areas
- New construction and renovations to classroom buildings and student spaces
- Improvements to safety, accessibility and sustainability across campus
As we move through each phase, there may be times when certain buildings or areas of the campus are unavailable. We are actively developing plans to ensure instruction and all student programs continue safely and effectively during these transitions. While no final decisions have been made about the use of temporary spaces, please know that every option is being carefully considered with student safety and educational quality as our top priorities.
We know that change brings questions and concerns. We are working closely with district leaders, architects, construction professionals and staff to address every aspect of the transition, including:
- Instructional Schedules: Adjusting bell schedules and class locations to ensure students have access to all required courses and programs, including specialized areas like career and technical education, athletics and fine arts.
- Student Experience: Maintaining the “Wildcat experience” and school spirit, even as some classes and activities may temporarily move to new or reconfigured spaces.
- Lunch and Transportation: Planning for meal service and transportation, especially as some students and staff may be learning or teaching in different buildings or locations.
- Safety and Access: Ensuring safe pathways, secure fencing and clear separation of student groups as needed.
- Staff and Family Needs: Addressing parking, attendance and communication so everyone stays informed and supported.
This message is among the many updates you will receive throughout the renovation process. We are committed to:
- Transparency: Sharing what we know, what is still being decided, and how you can stay informed.
- Timely Updates: Providing regular reports, visuals, and FAQs as plans develop and construction progresses.
- Listening: Welcoming your questions and feedback to help us make this transition as smooth as possible.
Next Steps
- We will share more detailed information about the 2025-2026 school year during the weeks and months ahead, including what to expect and how to prepare.
- A dedicated section on our website will soon house renovation updates, timelines and other information.
We are grateful for your partnership and patience as we embark on this exciting new chapter for our Wildcats. Working together, we can ensure that our students, staff and families continue to thrive, now and in the future.
Sincerely,
Kennitra Robertson, Principal
Plano Senior High School